Hyderabad Metro Expansion Faces Centre-State Hurdles

0
1
Hyderabad Metro Expansion Faces Centre-State Hurdles
Hyderabad Metro Expansion Faces Centre-State Hurdles

Hyderabad Metro Expansion | Hyderabad, Nov. 29: Hyderabad Metro Rail has completed nine successful years, carrying nearly 94.2 crore passengers since its launch. However, political differences between the Congress and BJP have cast a shadow over its expansion plans.

Despite repeated appeals by the Telangana government, the Centre has not cleared the proposals for the second phase. Meanwhile, the acquisition process linked to the first phase has also made little progress.

The delays have raised concerns among city commuters, who expect Metro expansion to ease Hyderabad’s growing traffic congestion.

Here To Join Us On WhatsApp

Metro Completes Nine Years, Carries 94.2 Crore Passengers

Prime Minister Narendra Modi and then Chief Minister K. Chandrashekar Rao inaugurated Hyderabad Metro Rail on November 28, 2017. Services opened to the public in phases from the following day.

ALSO READ: Gold Rates Today In Hyderabad On Nov. 29, 2026

Since then, the Metro has emerged as a major part of Hyderabad’s public transport network. It has carried approximately 94.2 crore passengers over nine years.

Hyderabad Metro Expansion Faces Centre-State Hurdles
Hyderabad Metro Expansion Faces Centre-State Hurdles

According to officials, around 4.5 lakh passengers use Metro services daily. The highest single-day ridership reached 5.2 lakh passengers.

The service connects several major routes and commercial centres across the city. It has become particularly useful for employees and students travelling to offices and educational institutions.

Metro services also help passengers avoid road congestion and reduce travel time. As an electric-powered transport system, the network contributes to efforts to reduce urban pollution.

Here To Join Us On WhatsApp

Hyderabad Metro Expansion | Second Phase Cost Rises by ₹4,330 Crore

While passenger numbers continue to grow, the expansion plans remain uncertain. The Telangana government has submitted proposals for the second phase to the Centre, but approval is still pending.

The estimated project cost has increased from ₹34,260 crore in November 2024 to ₹38,590 crore in the latest proposal. This represents an increase of ₹4,330 crore.

Officials reportedly say the Centre has not shown willingness to discuss the state government’s proposals at the Public Investment Board (PIB).

Chief Minister A. Revanth Reddy has met Prime Minister Narendra Modi and Union ministers several times. However, these meetings have not produced a breakthrough.

Metro Rail officials have also held repeated discussions with central government officials. Yet, the proposals remain without a final decision.

ALSO READ: Chicken Prices Rise In Telangana And Andhra Pradesh

The Telangana government has also faced difficulties in securing a loan for the acquisition of the first phase. Consequently, the process has not moved forward as expected.

Officials believe that timely approval of the second phase would help address Hyderabad’s growing traffic problems.

Here To Join Us On WhatsApp

Municipal Elections Could Influence Metro Decisions

The proposed municipal elections have also become part of the political discussion surrounding the project.

Elections to the GHMC and other municipal corporations in the city region are expected to take place after the MLC elections, according to current speculation.

Political analysts believe that clarity on the election schedule could influence the pace of decisions. Congress and BJP leaders reportedly see a possibility of progress on the first-phase acquisition and second-phase approval ahead of the municipal polls.

However, the timing and outcome of these processes remain uncertain.

Here To Join Us On WhatsApp

Hyderabad Metro Expansion | New HMRL MD Faces Major Challenges

The Telangana government issued orders on Saturday appointing Ajith Reddy as the new Managing Director of Hyderabad Metro Rail Limited (HMRL).

The new MD faces several important challenges, including completing the first-phase acquisition process and securing central approval for the second phase.

He will also have to focus on maintaining the existing 69-km Metro network and improving passenger facilities.

Here To Join Us On WhatsApp

Officials are expected to prioritise first-mile and last-mile connectivity. Better connections between Metro stations and residential areas, workplaces and other transport services remain essential.

As Hyderabad Metro enters its tenth year, commuters are looking for expansion and better connectivity. However, the project’s future progress will depend heavily on decisions by both the state and central governments.