Hyderabad Old City Metro Rail Works Face Fresh PIL Challenge

Hyderabad, August 6: The Telangana High Court on Wednesday continued hearing a Public Interest Litigation (PIL) seeking to halt Hyderabad Old City Metro Rail works in the Charminar Heritage Precinct, Falaknuma Heritage Precinct, and other notified heritage zones until statutory approvals and a Heritage Impact Assessment are completed.

Here To Join Us On WhatsApp

The petition was filed by the Act Public Welfare Foundation (APWF), represented by its president, Mohammed Rahim Khan. It seeks suspension of construction until authorities comply with the Telangana Heritage Act, 2017, and the Ancient Monuments and Archaeological Sites and Remains Act, 1958.

Hyderabad Old City Metro Rail Works Under Court Scrutiny

The petitioner argued that the government initially claimed the Metro project would not affect any heritage or religious structures. However, it later acknowledged that three structures were impacted. He further claimed official records identify six Grade 1 heritage structures and 102 heritage and sensitive structures along the proposed route.

Here To Join Us On WhatsApp

The petitioner also told the court that photographs submitted as evidence showed damage to certain structures, despite the government’s claim that no demolition had taken place.

Meanwhile, the State government opposed the PIL and termed the allegations incorrect. Additional Advocate General Mohammed Imran Khan informed the court that only a few notified heritage structures fall along the Metro alignment. He said several identified buildings would neither be acquired nor disturbed.

The government submitted a detailed affidavit explaining the status of each heritage structure on the proposed corridor. It assured the court that no acquisition or demolition would occur without following the legal process, including denotification wherever necessary.

Here To Join Us On WhatsApp

Referring to photographs, the government maintained that heritage structures such as Aliabad Sarai and the old MCH building at Darulshifa remain intact. It added that while some nearby private properties were removed, no notified heritage building had been demolished.

However, the petitioner argued that the issue concerns the protection of entire heritage precincts rather than only individual buildings. He contended that any construction affecting a notified heritage zone requires prior statutory approval, even if no listed structure is directly acquired.

Here To Join Us On WhatsApp

After hearing both sides, the High Court said it would examine all submissions and documents before issuing further directions. The matter has been posted for the next hearing on August 27.

Now you can get the latest stories from Indtoday on Telegram every day. Click the link to subscribe.  Click to follow Indtoday’s Facebook pageTwitter, and Instagram. For all the latest Hyderabad News updates and Follow us on GoogleNews