Construction Of Medigadda Seventh Block Not As Per Plan: V & E

Hyderabad, Feb 15 (Maxim News): Vigilance and Enforcement, which investigated, stated that everything from the construction to the maintenance of the medigadda barrage was flawed, and the contractor company and the irrigation department had violated the contract in many aspects.

Click Here To Join Us On WhatsApp 

It advised the government to set up an expert committee to find out the reasons for the failure and plan for recovery. Director of Vigilance and Enforcement Rajeev Ratan not only submitted a report to the government on the issues found under their observation but also gave many details during the visit of the Chief Minister, Ministers, and MLAs to medigadda barrage on Tuesday.

The construction of the seventh block in Medigadda Barrage is not as planned. The construction of rafts and secant piles was not done properly. Not as per plan (drawing). This is a major cause of loss. Cracking of piers 16 to 21 and loss of supporting material may cause raft failures. This is due to the construction company L&T.

Click Here To Join Us On WhatsApp 

The barrage has not been maintained since its inception on June 21, 2019, in 2019 itself, the problem worsened as the CC blocks shifted sideways and the plinth slab parametric joint was ignored. The reason for this is the construction company and irrigation department.

The construction company ignored several letters written by the irrigation department to repair the damaged works. Letters were written on May 18, 2020, February 17, 2021, April 6, 2022, and April 23, 2023, but no response. However, the engineers gave certificates that the work was completed contrary to the contract.

Click Here To Join Us On WhatsApp 

Even after the construction of the barrage, the cofferdam and sheet piles were not removed. They have not been eliminated in five seasons. This affected the flow of the river. As per the agreement, the work related to the delivery of the barrage has not been done. This is due to the construction company.

According to the Dam Safety Act, the barrage should be inspected before and after the monsoon season.  If anything is found in this inspection, it should be reported to the state dam safety authorities and steps should be taken.  However, such checks do not appear to have been carried out.

Click Here To Join Us On WhatsApp 

It is alleged that the major blocks in the barrage were constructed by a sub-contractor. This matter is under investigation. We are investigating the accounts.

Bank guarantees have been released even though the works are pending. The reason for this is the irrigation department. (Maxim News) 


Next Story :

  • HYDRA Razes Illegal Structures In Sangareddy

    HYDRA Razes Illegal Structures In Sangareddy

    Sangareddy/Hyderabad, Nov 18 (Maxim News): HYDRA officials today carried out demolitions in Ameenpur Municipality. Illegal construction in Vandanapuri Colony in Survey number 848 was carried out. Some people occupied the road and started the construction of houses.


  • Telangana Secretariat: Architectural changes in Telangana Secretariat

    Telangana Secretariat: Architectural changes in Telangana Secretariat

    Telangana Secretariat | Hyderabad, November 18: Minor architectural changes are going on in the Dr. BR Ambedkar Telangana State Secretariat. Click Here To Join Us On WhatsApp The main gate on the east side (Bahubali Dwaram) is being closed. As part of this, the doors were removed and petals were placed in that area. Click…


  • Prematurity Awareness Walk Held At West Marredpally

    Prematurity Awareness Walk Held At West Marredpally

    A walk for a unique cause—”Prematurity Awareness”—was held in the city today from Parade Grounds to Pushpagiri Vitreo Retina Institute(PVRI) West Marredpally. The walk was organized to bring attention to the challenges faced by babies and families born prematurely. It was organized on the eve of World Prematurity Day, which is celebrated on November 17th.


  • Maha Annakut Mahotsav held at Goushala Satyam Shivam Sundaram Gau Nivas

    Maha Annakut Mahotsav held at Goushala Satyam Shivam Sundaram Gau Nivas

    South India’s biggest and India’s best maintained Gaushala (cow shelter) Satyam Shivam Sundaram Gau Nivas organized “Maha Annakut Mahotsav”  in the city at  Umda Nagar in Gaganpahad.


Now you can get the latest stories from Indtoday on Telegram every day. Click the link to subscribe.  Click to follow Indtoday’s Facebook pageTwitter and Instagram. For all the latest Hyderabad News updates

Leave A Reply

Your email address will not be published.